Developer approved the plans on the 4th of February 2013 yay !!!!!!!
According to Oran park design guidelines panel, they give a decision within 2 weeks but as usual nothing is on time and we had our approval after 3 weeks instead.
Now our customer support officer will be ordering the DA pack to be lodged into the council. the time frame from Camden council is 6-8 weeks. Geez that's a while to wait and if everything goes smoothly.
Now our customer support officer will be ordering the DA pack to be lodged into the council. the time frame from Camden council is 6-8 weeks. Geez that's a while to wait and if everything goes smoothly.
DA pack ready on the 15 of February 2013. took exactly 2 weeks to get it ready. Now our CSO will be sending the application off to Camden council
Well unfortunately for us, our CSO was sick for 1 week so I had to call several times to their management, to get the application sent to the council, since my file was sitting on my CSO's desk for a whole week without anyone touching it. After my conversation with the management team, another CSO sent my file to council.
DA lodged to the council website on the 22 of February 2013