Saturday 1 June 2013

Slabbed !!!!!!



     Pouring the slab finally happened !!!! YAY !!! it was a very big surprise for us, we didn't expect it to happen that quick. They done the piering and plumbing on the 29th of May and SS told us it should take 1 week for the concrete to settle so it would be next week that the slab would be poured. So I thought I had time to take pictures during the weekend.
    So We went to the site on Saturday to take pictures of the piering but when we got there we saw many trucks and around 6 tradies on our land laying the slab. Wow they were working on a Saturday, so obviously I was around the fence taking thousands of pictures and videos : )
    1 hour after the tradies left, it started to rain so I was a little bit worried about the slab losing his shape or falling apart. But from my previous researches I saw that rain help the slab to cure and prevent the slab from cracking. I quickly confirmed it with  a tradie that was working on the neighbor's site.
It took 10 days from site cut to slab being laid







No comments: